Construction |
Bridge over the village stream in Sohland a.d.Spree |
|
|
|
Year: |
|
2017 |
|
|
|
Services: |
|
Statics |
|
|
|
|
|
|
Construction |
Hydroelectric power plant Lastauer Mühle, building a trash rack cleaning systems |
|
|
|
Year: |
|
2016 |
|
|
|
Services: |
|
Statics |
|
|
|
Detail: |
|
trash track |
|
|
 |

|
|
|
|
|

|
 |
Construction |
Hydroelectric power plant Waagmühle an der Schwalm |
|
|
|
Year: |
|
2017 |
|
|
|
Services: |
|
Statics |
|
|
|
Detail: |
|
draft tube |
|
|
|
|
|
|
Construction |
Waterworks Hosterwitz |
|
|
 |
|
|
|
|
|
|
 |
Construction |
Bridge over the Gramme in Werningshausen |
|
|
|
Year: |
|
2016 |
|
|
|
Services: |
|
form- and reinforcement plans |
|
|
|
Detail: |
|
reinforcement abutment |
|
|
|
|
|
|
Construction |
Bridge over the Witzbach in Hainichen |
|
|
|
Year: |
|
2016 |
|
|
|
Services: |
|
Statics |
|
|
 |
|
|
|
|
|

|
 |
Remedation |
Hydroelectric power plant Mühle Lauter, Remedation intake structure |
|
|
|
Year: |
|
2016 |
|
|
|
Services: |
|
Statics |
|
|
|
|
|
|
Construction |
Hydroelectric power plant Lunzenau, Construction a fish ladders |
|
|
|
Year: |
|
2016/17 |
|
|
|
Services: |
|
Statics |
|
|
|
Detail: |
|
reinforcement of the wall |
|
|
 |

|
|
|
|
|
|
 |
Construction |
Hydroelectric power plant Alt in Rohrbach |
|
|
|
Year: |
|
2016 |
|
|
|
Services: |
|
Statics |
|
|
|
|
|
|
Remedation |
Hydroelectric power plant Mauer a.d. Elsenz |
|
|
 |
|
|
|
|
|
|
 |
Construction |
Bridge in Langenhennersdorf |
|
|
|
Year: |
|
2016 |
|
|
|
Services: |
|
Statics |
|
|
|
|
|
|
Extension |
Balkony by the apartment building Zwickauer Str. |
Year: |
|
2017 |
|
|
|
Services: |
|
Genehmigungs- und Ausführunsplanung, Statics |
|
|
|
Detail: |
|
anchoring the balkony |
|
|
 |

|
|
|
|
|
|  |
Construction |
Hydroelectric power plant Mühlhof, Retaining wall |
|
|
|
|
|
|
Construction |
Hydroelectric power plant Ewattingen |
|
|
|
Year: |
|
2014 |
|
|
|
Services: |
|
Statics |
|
|
|
Detail: |
|
Suction pipe |
|
|
 |

|
|
|
|
|
|
 |
Construction |
Hydroelectric power plant Stockach, Contruction of a Hydroelectric power plant |
|
|
|
Year: |
|
|
|
|
|
Services: |
|
Zoning permit planning |
|
|
|
|
|
|
|
|
|
|
|
|
Construction |
Hydroelectric power plant Singen, Contruction of a residual water turbine with fish ladders |
|
|
|
Year: |
|
|
|
|
|
Services: |
|
Zoning permit planning |
|
|
|
|
|
|
|
 |
|
|
|
|
|

|
 |
Construction |
Hydroelectric power plant Geisenfeld, construction a fish ladders |
|
|
|
Year: |
|
2013 |
|
|
|
Services: |
|
Zoning permit planning, Statics |
|
|
|
|
|
|
|
|
|
|
|
|
Construction |
Flood control storage reservoir Schelsbach, intake / outlet |
|
|
|
Year: |
|
2014 |
|
|
|
Services: |
|
Statics |
|
|
|
|
|
|
|
 |
 |
|
|
|
|
 |
 |
Construktion |
Hydroelectric power plant Lewitzschleuse, installation of a new turbine |
|
|
|
Year: |
|
2013 |
|
|
|
Services: |
|
Statics |
|
|
|
|
|
|
|
|
|
|
|
|
Construction |
Hydroelectric power plant Fahlenbach, construction a fish ladders |
|
|
|
Year: |
|
2013 |
|
|
|
Services: |
|
Zoning permit planning, Statics |
|
|
|
|
|
|
|
 |

|
|
|
|
|

|
 |
Remediation |
Hydroelectric power plant Colditz, Remedation weir system |
|
|
|
Year: |
|
2012 |
|
|
|
Services: |
|
Statics |
|
|
|
Detail: |
|
reinforcement weir system |
|
|
|
|
|
|
Construction |
Hydroelectric power plant in castle mill Rochlitz, construction a fish ladders |
|
|
|
Year: |
|
2012 |
|
|
|
Services: |
|
Statics |
|
|
|
|
|
|
|
 |

|
|
|
|
|
|
 |
Remediation |
Bridge in Wiederau |
Year: |
|
2012 |
|
|
|
Services: |
|
Statics, Detailed design |
|
|
|
|
|
|
|
|
|
|
|
|
Replacement |
Hydroelectric power plant in Oschersleben |
|
|
|
Year: |
|
2013 |
|
|
|
Services: |
|
Statics, factory planning |
|
|
|
|
|
|
|
 |
|
|
|
|
|

|
 |
Construction |
Bio-energie and bio-fuel-centrum Bad Köstritz, construction a reception silo |
|
|
|
Year: |
|
2011/12 |
|
|
|
Services: |
|
Statics, Detailed design |
|
|
|
Detail: |
|
reinforcement expansion |
|
|
|
|
|
|
Construction |
Hydroelectric power plant Hetzdorf, Construction a hydrodynamic screws |
|
|
|
Year: |
|
2011 |
|
|
|
Services: |
|
Statics |
|
|
|
|
|
 |

|
|
|
|
|

|
 |
Construction |
Hydroelectric power plant Buchersried, construction a fish ladders |
Year: |
|
2012 |
|
|
|
Services: |
|
Statics, Detailed design |
|
|
|
|
|
|
|
|
|
|
|
|
Construction |
Hydroelectric power plant Hohenwart, construction a gate stays and a fish ladders |
|
|
|
Year: |
|
2012 |
|
|
|
Services: |
|
Statics, factory planning |
|
|
|
Detail: |
|
gate stay |
|
|
 |

|
|
|
|
|

|
 |
Construction |
Hydroelectric power plant, construction of a gate stays |
Year: |
|
2012 |
|
|
|
Services: |
|
Statics, factory planning |
|
|
|
Detail: |
|
construction of a gate stays |
|
|
|
|
|
|
Construction |
transportable forklifts bridge |
|
|
|
Year: |
|
2012 |
|
|
|
Services: |
|
Statics |
|
|
|
|
|
 |

|
|
|
|
|

|
 |
Alteration |
Cordenka, Alteration spinning mill and textile business |
|
|
|
Year: |
|
|
|
|
|
Services: |
|
design planning |
|
|
|
|
|
|
|
|
|
|
|
|
Construction |
Construction residual water turbine, Aggerdam |
|
|
|
Year: |
|
2011 |
|
|
|
Services: |
|
Zoning permit planning |
|
|
|
Detail: |
|
residual water turbine |
|
|
 |

|
|
|
|
|

|
 |
Construction |
Hydroelectric power plant, downstream fish passage |
|
|
|
Year: |
|
2012 |
|
|
|
Services: |
|
Statics |
|
|
|
|
|
|
|
|
|
|
|
|
Construction |
RAWEMA-building, construction rescue stairway |
|
|
|
Year: |
|
2011 |
|
|
|
Services: |
|
factory planning |
|
|
|
Detail: |
|
bracing connection |
|
|
 |

|
|
|
|
|

|
 |
Construction |
Bridge over the Bahrebach |
Year: |
|
2011 |
|
|
|
Services: |
|
Statics |
|
|
|
|
|
|
|
|
|
|

|
 |
Construction |
Construction of a rescue stairway from school in Erdmannsdorf |
|
|
|
Year: |
|
2010 |
|
|
|
Services: |
|
Statics |
|
|
|
Detail: |
|
fixing on the building |
|
|
|
|
|
|
|
|
|
|

|
 |
Remediation |
facade of Komplement , clinic in Chemnitz |
|
|
|
Year: |
|
2009/2010 |
|
|
|
Services: |
|
Statics |
|
|
|
Detail: |
|
fixing sun protection |
|
|
|
|
|
|
Construction |
Rail link Bamberg-Fürth, Retaining wal with noise barriers |
|
|
|
Year: |
|
2009-2013 |
|
|
|
Services: |
|
Detailed design |
|
|
|
Detail: |
|
bored pile walls |
|
|
 |

|
|
|
|
|

|
 |
Construction |
Hydroelectric power plant Höllmühle, Construction Krafthaus |
|
|
|
Year: |
|
2009 |
|
|
|
Services: |
|
Statics, Detailed design |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|

|
 |
Construction |
Hydroelectric power plant Colditz,installation hoizontal rake and fish pass Fischaufstiegshilfe |
Year: |
|
2007 |
|
|
|
Services: |
|
Statics, Detailed design |
|
|
|
Detail: |
|
fish pass |
|
|
|
|
|
|
Construction |
Extension the noise barriers allong the B252 |
|
|
|
Year: |
|
2007 |
|
|
|
Services: |
|
Statics, Detailed design |
|
|
 |

|
|
|
|
|

|
 |
Construction |
Retaining wall of the ICE-Route in Erfurt |
|
|
|
Year: |
|
2007-08 |
|
|
|
Services: |
|
Detailed design |
|
|
|
Detail: |
|
side view retaining wall |
|
|
|
|
|
|
Construction |
Retaining wall allong the B6 in Meissen |
|
|
|
Year: |
|
2006 |
|
|
|
Services: |
|
Statics, Detailed design und SIGE |
|
|
|
Detail: |
|
fixtur in stock |
|
|
 |

|
|
|
|
|

|
 |
Construction |
Bridge in Flöha |
|
|
|
Year: |
|
2006 |
|
|
|
Services: |
|
Statics |
|
|
|
|
|
|
|
|
|
Construction |
bioenergy and biofuel-centrum in Bad Köstritz |
|
|
|
Year: |
|
2006-07 |
|
|
|
Services: |
|
Statics, tender of construction, outside facilities |
|
|
|
Detail: |
|
placing of concrete |
|
|
 |

|
|
|
|
|

|
 |
Construction |
Hydroelectric power plant Mittweida |
|
|
|
Year: |
|
2005-06 |
|
|
|
Services: |
|
Statics, Detailed design |
|
|
|
Detail: |
|
turbine chamber |
|
|
|
|
|
|
Construction |
Hydroelectric power plant Haselmühle |
|
|
|
Year: |
|
2005 |
|
|
|
Services: |
|
Statics, Detailed design |
|
|
|
Detail: |
|
horizontal rake |
|
|
 |

|
|
|
|
|

|
 |
Construction |
Bridge over the river Hegebach in Gersdorf |
|
|
|
Year: |
|
2004-05 |
|
|
|
Services: |
|
Statics |
|
|
|
Speciality: |
|
Less expensive alternative solution |
|
|
|
|
|
|
Construction |
Retaining wall in the castle park Wesenstein |
|
|
|
Year: |
|
2004-05 |
|
|
|
Services: |
|
Statics |
|
|
 |

 |
|
|
|
|
 |
 |
Construction |
Mounting for traffic signs at the tunnel entrance Altfranken of the A17 |
|
|
|
Year: |
|
2004 |
|
|
|
Services: |
|
Statics, shop drawings |
Detail: |
|
Mounting bridge |
|
|
|
|
|
|
Construction |
Base for noise barriers allong the A72 |
|
|
|
Costs: |
|
Approx. 705.000 Euros |
|
|
|
Year: |
|
2004-05 |
|
|
|
Services: |
|
Statics |
|
|
 |
 |
|
|
|
|
 |
 |
Construction |
Parking lot for Buschbeck Solartechnik GmbH in Erdmannsdorf |
|
|
|
Costs: |
|
Approx. 70,000 Euros |
|
|
|
Year: |
|
2004 |
|
|
|
Services: |
|
Overall design |
|
|
|
|
|
|
Construction |
Retaining wall Ahnerweg in Burkhardtsdorf |
|
|
|
Year: |
|
2004-05 |
|
|
|
Services: |
|
Statics, Safety And Health Protection (SiGE) |
|
|
 |
 |
|
|
|
|

|
 |
Replacement |
Bridge over the river Kemnitzbach in Wingendorf |
|
|
|
Year: |
|
2004 |
|
|
|
Services: |
|
Statics |
|
|
|
|
|
|
Remediation |
Bridge pier in Erdmannsdorf |
|
|
|
Costs: |
|
Approx. 40,000 Euros |
|
|
|
Year: |
|
2004 |
|
|
|
Services: |
|
Overall design, construction supervision |
|
|
|
Detail: |
|
Reinforcement of the fundation |
|
|
 |

|
|
|
|
|

|
 |
Reconstruction |
Bridge over the river Zschopau in Kunnersdorf |
|
|
|
Costs: |
|
Approx. 0.5 m DM |
|
|
|
Year: |
|
1997 |
|
|
|
Services: |
|
Overall design, construction supervision |
|
|
|
|
|
|
Construction |
Hydroelectric power plant Penig |
|
|
|
Year: |
|
2004 |
|
|
|
Services: |
|
Design of the barrage including shop drawings of the throttle plate |
|
|
 |
 |
|
|
|
|

|
 |
Construction |
Hydroelectric power plant Biebermühle near Penig |
|
|
|
Costs: |
|
Approx. 1.5 m DM |
|
|
|
Year: |
|
2000 |
|
|
|
Services: |
|
Overall design |
|
|
|
|
|
|
Construction |
Hydroelectric power plant in Amerika near Penig |
|
|
|
Costs: |
|
Approx. 3.2 m DM |
|
|
|
Year: |
|
1997 |
|
|
|
Services: |
|
Overall design, construction supervision |
|
|
|
Detail: |
|
Suction pipe in the turbine building |
|
|
 |

|
|
|
|